Power Outage in Claremont, Johannesburg
Power Outages Affecting Claremont1 active
Updated 2m ago- Update - Wed, 01 Jul, 12:24Latest updates are available regarding the Hursthill outage.source
- Update - Fri, 03 Jul, 11:00A replacement indoor transformer has been delivered to Hursthili Substation TSS Newlands for installation, affecting customers on Italian Road, Stonewall Road and Market Road in Newlands following a previous explosion.source
- Update - Sat, 04 Jul, 10:32Repairs are currently underway at Hurshill Substation (TSS Newlands), affecting customers at Italian Road, Stonewall Road, and Market Road in Newlands.source
- Reported - Sat, 04 Jul, 18:36Insulation at the Italian transformer substation was damaged by fire, affecting customers on Italian Road, Stonewall Road and Market Road in Newlands. The repair team will resume work tomorrow morning.source
- Reported - Sun, 05 Jul, 09:01An outage is affecting customers in Claremont, and operators have been notified to investigate the cause.source
- Update - Mon, 06 Jul, 10:34Repairs on a low voltage fault affecting customers on Italian Road, Stonewall Road and Market Road in Newlands have been completed, with final checks and supply restoration to follow.source
- Reported - Mon, 06 Jul, 12:53Infrastructure inside the transformer switching station exploded and caught alight during final checks on low voltage repairs, affecting customers on Italian Road, Stonewall Road and Market Road.source
- Update - Mon, 06 Jul, 13:16An explosion damaged two circuit breakers and leads from the transformer at Hursthull Substation's Claremont 11kV distributor, affecting customers on Italian Road, Stonewall Road, and Market Road.source
- Update - Tue, 07 Jul, 07:52A contractor has been appointed and material is being sourced for repairs at Hursthills Substation, Claremont 11kV distributor.source
Other outages in this area
Reports from nearby suburbs in the same City Power service area. Not necessarily affecting Claremont directly.
Johannesburg Power Outages Today3 active
Updated 2m ago- Update - Sat, 04 Jul, 10:40Repairs are in progress at Johnware Substation's Forsburg South Distributor, affecting customers at Honover street, 5th & 6th Avenue and Park drive in Mayfair.source
- Update - Sat, 04 Jul, 13:13Repairs have been completed at Johnware Substation's Forsburg South Distributor, affecting customers at Honover street, 5th & 6th Avenue and Park drive in Mayfair; final tests are pending before restoration.source
- Update - Sat, 04 Jul, 17:00Repairs are concluded in Honover street, 5th & 6th Avenue and Park drive in Mayfair, and the operation team will proceed with the restoration process.source
- Update - Sat, 04 Jul, 21:43Supply has been 100% restored on Honover street, 5th & 6th Avenue and Park drive in Mayfair, following a faulty cable.source
- Update - Mon, 06 Jul, 19:39The fault at Johnware Substation was located under the tunnel, and a contractor will carry out repairs tomorrow morning, affecting customers at Vlak Street, Scraper Street, and True Road in Selby.source
- Update - Tue, 07 Jul, 12:04Repairs are underway at Johnware Substation following a cable theft reported on Sunday, 05 July, affecting customers on Vlak Street, Scraper Street, True Road, and other possible streets in Selby.source
- Update - Tue, 07 Jul, 14:01Approximately 140 meters of cables were burned inside the tunnel at Johnware Substation due to cable theft, affecting customers on Vlak Street, Scraper Street, True Road, and other streets in Selby.source
Report a Power Outage in Claremont
Is your power off in Claremont? Report it to City Power so they can dispatch a team.
When Will Electricity Come Back in Claremont?
How long a power outage in Claremont takes to fix depends on what caused it. These are the typical restoration times for the three fault categories City Power handles.
- Unplanned fault
- Most outages in Claremont fixed within 4-8 hours. Minor faults (tripped circuit) take 2-4 hours.
- Cable theft
- 12-48 hours to repair, especially if specialised equipment is needed.
- Planned work
- City Power notifies Claremont residents in advance. Usually 6-10 hours during the day.
Power Outage History for Claremont (Last 90 Days)
City Power reported 2 outages affecting Claremont in the last 90 days, totalling 121.7 hours without power. Average restoration time was 60.8 hours. Most faults traced back to the Hursthill Substation substation (2 of 2). The most common cause was cable fault.
| Date | Duration | Substation | Cause | Also affected |
|---|---|---|---|---|
| 05 Jun 2026 | 9.3h | Hursthill Substation | cable fault | Coronationville, Westbury, Northcliff, Triomf +4 more |
| 24 Apr 2026 | 4.7d | Hursthill Substation | needs oil top up | Newlands, Hurst Hill, Westbury, Princess +3 more |
What to Do During a Power Outage in Claremont
Quick checklist to follow while waiting for City Power to restore power in Claremont.
- Switch off appliances at the wall to prevent damage from power surges when electricity returns.
- Leave one light switched on so you know when power is restored.
- Keep fridges and freezers closed - food stays cold for 4-6 hours if unopened.
- Use battery-powered lights instead of candles to reduce fire risk.
- Report the outage to City Power on 0114907484 / 0860562874 if it has not been reported yet.
Frequently Asked Questions About Power Outages in Claremont
Is there a power outage in Claremont right now?
Yes, there is currently a power outage reported in Claremont, Johannesburg. City Power is aware and working on restoration. Check the live updates above for the latest status and estimated restoration time.
How do I report a power outage in Claremont?
Call City Power on 0114907484 / 0860562874 to report a power outage in Claremont. You can also report online at citypower.co.za or follow @CityPowerJhb on X (Twitter) for updates.
How long do power outages last in Claremont?
Most unplanned power outages in Claremont are fixed within 4-8 hours. Minor faults like tripped circuits are often restored in 2-4 hours. Major faults from cable theft or equipment damage can take 12-48 hours. Planned maintenance typically lasts 6-10 hours during the day.
When will the electricity be back on in Claremont?
For the active outage affecting electricity in Claremont, see the live update at the top of this page for City Power's latest restoration estimate. Most unplanned electricity outages in Claremont restore within 4-8 hours. Call 0114907484 / 0860562874 to confirm the ETA for your specific street.
Is it load shedding or a power outage in Claremont?
If your power is off outside the load shedding schedule, Claremont is experiencing an unplanned power outage - not load shedding. Load shedding follows a fixed timetable, while power outages are caused by faults, cable theft, or equipment failure. Check Claremont load shedding schedule
What number do I call for City Power in Claremont?
Call City Power on 0114907484 / 0860562874 for power outages in Claremont. You can also report faults online at citypower.co.za or WhatsApp the relevant SDC channel for your area.
Related Pages
Click here to join our telegram channel and stay up to date with load shedding and related news!